HOUSE Elemental House
LOCATION Dooralong, NSW
INITIAL BUDGET $1 million
FINAL COST $1.2 million
DATE COMMENCED August 2018
DATE COMPLETED March 2021
this beautiful dwelling, a triumph of exceptional design, materiality and innovation, is the latest offering for Grand Designs Australia.
When the final nail was hammered into place, designer and builder Mick Heuchan says it was an emotional moment. “It was almost surreal that it was finally finished, it's what I'd been dreaming about for the last 10 years or more,” he says.
Mick had envisioned a house